By Karen Gleason
The 830 Times
Val Verde County Commissioners Court members heard an update on several major projects the county has underway during their November regular term meeting Wednesday, Nov. 18.
County Judge Lewis G. Owens Jr. introduced the update, reminding the court it would not be able to take action on any of the projects. He then asked County Engineer Carlos Velarde to give the project updates.
Owens noted there were several residents of the county’s Escondido Estates colonia in the audience and said, “We have been, since Commissioner Pct. 1 Martin Wardlaw was here, working on the booster pumps, the booster station, (in Escondido), so we’ve gone from $355,000, to $815,000, to $370,000, so we’re under $400,000 right now. That contract’s been awarded, and they’re working on that, but the rest of that question is what happens later, right?
“Escondido had a bunch of water lines that we’d run that were not connected, so they don’t help with the flow or the pressure in Escondido. This system’s going to help, and I’m going to let (Velarde) go through the $1 million that we have borrowed, that way we can tell you what’s going to be the next step, moving forward.
“So, the Escondido project, the money’s there, it’s been set aside, they’re working on it, and it’s very close to being complete. We don’t have to wait on anybody anymore, to get it done,” Owens said.
Velarde began his presentation by discussing a $5 million Defense Economic Adjustment Assistance Grant for modernization and repair of airfield lighting at Laughlin Air Force Base.
Velarde told the court, “We still have another year to complete this project, until January 2028. It’s part of a $12 million project to take care of all the upgrades on their airfield lighting.”
Velarde next addressed work being done to qualify the county for funding under a Federal Emergency Management Agency disaster declaration for Texas covering infrastructure damage from storms, straight-line winds, tornadoes and floods in the summer of 2026.
The engineer said, “We’re currently waiting on FEMA and working with them, in tracking all the damage inventory, site inspections and intake for the grants portal project scoping for FEMA and TDEM. We’ll be meeting with TDEM and FEMA on Friday, Nov. 20, and we’re shooting for the Dec. 16 deadline for applications to be complete.”
Velarde said he has been working with all four precincts to track personnel and equipment hours for repairs.
The next update was on the Val Verde County Gun Range Facility.
Velarde said, “On this one, we have a total contract for $3,028,000, and we have three change orders, which were the indoor partition walls,

the data room mini-split, which IT requested an additional separate unit for that room, and then the front counter and kitchen cabinets.”
He said the performance period for the project was Aug. 22, 2025, to Dec. 22, 2026.
Velarde said, “At this moment, the project is 80 percent complete. The next critical items on this project is the electrical underground connections with Rio Grande Electric Co-op. That’s taken a little longer than expected.
“The TxDOT (Texas Department of Transportation) driveway is under construction and they’re going to bore in an 8-inch water line from the other side of the highway, and they’re also working on the parking lot and the site grading. Indoors, they’re working with the ceiling tiles and painting the metal structure. They’re doing electrical work, and outside they’re beginning to work on the driveway entrance, the septic and the site work.”
“It’s going to be hard to finish within a month, but we’re going to try our best,” Velarde said.
Velarde next discussed three projects that were part of a Colonia Fund Construction grant.
Velarde said, “Those projects are the Comstock water tank, the Vega Verde water lines and the San Felipe Pastures booster station.”
Velarde said the Comstock water tank project is complete “and is already working and in service.”

County. The water tank was one of three projects the county took on using state Colonia Fund
Construction monies. (Courtesy photo)
Owens noted the county can apply for another $1 million grant through the Texas Water Development Board, but the three colonia fund projects must be completed first.
Owens said, “We’ve got San Felipe Pastures that is not done completely yet, and we’ve got Vega Verde, where we still need some water lines, so depending on how we work between here and January, if we can get an extension, is whether it will allow us to apply for the next round of funding. We’ve run into this at least one other time since I’ve been judge. … In the next month-and-a-half, we’ll know whether or not we can apply for another round of funding.”
“For whatever those projects might be, something else in Comstock, San Felipe Pastures, Escondido, Vega Verde, but we’ve got to get done with these right now,” Owens added.
Precinct 3 Commissioner Fernando Garcia said he wanted to make a comment about the Comstock project.
Garcia said, “I wanted to thank the (county) judge personally, because of him, we discussed changing valves and stuff that wasn’t originally in the grant, and we ran into problems with connecting valves. I talked to him, and we got some money from the Comstock Water System and some money from the county – the judge was generous enough to find some money in the budget – and that’s why those two change orders were done, and that made the project a whole lot slicker. There’s going to be less problems in the future because we did change out a whole bunch of valves, so thank you, from the people of Comstock to you, judge.”
“Thank you to the court,” Owens responded.
Velarde resumed his presentation, saying the San Felipe Pastures booster station project is about 72% complete. The pump house has been built, the pumps are installed, and work continues on the heating and cooling system and the electrical connections to the pumps.
“They’ve already tapped into the city main on FM 2523. That’s already connected. We’re just waiting for power and then, we test everything,” Velarde said.
He addressed the third of the colonia construction projects, the Vega Verde water line extension. Velarde said the project is about 61% complete, with 5,100 of the planned 8,340 linear feet installed.
Velarde next spoke about the parking lot at the Roberto “Bob” Chavira Sports Complex. He said the county had awarded a $1.2 million contract for materials.
“Ongoing activities: They are doing the construction of the parking lot. They’re doing the site grading, using county crews from Precinct 2,” Velarde said.
Velarde said the county is now using its own recently installed GPS system to stake the site, a task that previously relied on TxDOT’s system.
Velarde then reviewed several improvements the county has made to comply with the Americans with Disabilities Act, including work at the juvenile probation office at 200 Griner St.
“That was completed yesterday (Tuesday, Nov. 17), 100 percent, and right now, the concrete is curing and waiting to be opened to traffic on Monday, Nov. 23. It looks really good, if you have time to go check it out. They put in two ramps. They put in all improvements to the parking, and I like the outcome on that project,” Velarde said.
Owens said the court set aside $300,000 for ADA compliance projects in the previous fiscal year and the county is still working on some of those projects.
“We did the parking lot here (at the courthouse), did the entrances over here, and then we’re going to move over to the Tony Faz County Annex,” Owens added.
Velarde said the next TxDOT ADA compliance project will be the parking lot at the Judge Antonio “Tony” Faz III County Annex, 315 E. Chapoy.
He said, “On that one, we received proposals last week, and we’re just waiting on the city of Del Rio building permit to begin, and the county purchasing agent to present an award for the contractor.”
Velarde then addressed the Escondido Estates booster station project.
Velarde told the court, “For this one, all the electrical upgrades are in place. The contract was for $386,799, and right now, all the submittals for the pumps were approved and we’re just waiting on the pumps to get here. They’re already ordered.”
Velarde finished his presentation with projects in the design phase, including the Cienegas and Duck Pond water crossing bridge, the concession stand at the Roberto “Bob” Chavira Sports Complex and grading for the complex’s fields.
The writer can be reached at delriomagnoliafan@gmail.com.